At the plant for the cleaning of airborne paint lines from steam of organic solvents is used installation of RTO Italian production. The installation has two towers filled with ceramic blocks used as heat-exchanging material during the regeneration of heat by thermal oxidation of organic compounds.
During operation, some of the ceramic blocks were destroyed due to periodic temperature disturbances, which led to the forced shutdown of the equipment.
Our specialists conducted a field technical audit of the RTO with the purpose of analysis of the reasons for the complex situation, on the basis of which were developed a number of recommendations for further operation of the installation.
It was recommended to completely replace all ceramic blocks that are more suitable for the requirements of the technological process.
We were selected ceramic blocks, which have the best technical characteristics:
At the same time, the cost of the blocks was even less than in the case of acquisition by the supplier of the installation.
These blocks were installed by our specialists at the RTO installation, the process of air purification was renewed.